Sunday, July 14, 2013

Final preparation for straw bales

At the end of June, while "Clay and Straw" finished a project in Central Texas, we added the inside 2x4's to make the "toe-up" for the bales to sit on, built  the stairs on the south side of the house and a ramp on the north side, to move plaster up onto the porch.  Pea gravel was delivered for the toe-up, an electrician and plumber were hired and Altumaxis, my solar panel provider, was notified the metal roof would be going on in mid-July. 


Boric acid to kill bugs
Pea gravel, acts like a french drain               
Roofing felt, another layer of moisture prevention

Nails to key bales to